Shop Renovation

Karaköy-Tophane Shop Renovation

Duration
2 weeks
İstanbul
Karaköy-Tophane
Karaköy-Tophane Shop Renovation

The renovation of a shop in Karaköy-Tophane was completed in just 15 days: drywall partitions, plastering and painting, floor screeding, and tile installation were all carried out back-to-back on a single schedule.

A turnaround this short for a shop fit-out depends on getting the work sequence right from the start — partitions, then screed, then tiling, then paint; the project followed that order and was delivered in 15 days.

Alçıpan bölme duvarZemin şap uygulamasıSeramik fayans

What Made This Project Work

Partitions, screed, tiling and paint carried out back-to-back on one schedule

Work sequence planned upfront to save time

Delivered in as little as 15 days